Today’s Update


The ballast boards are now all in place. Still some final levelling to do and paperwork before track can be run on. No signals or power points as Tom will be starting on those this next week. Water tank will not be plumbed for first open day so there will be one tap as planned at rear of station and a temp feed to the second tap which on the gantry. Both fed from mains. To get water tank up and running we need to finish derusting sort the large ball valve then pipe up. 