Sunday more done but there is still plenty to do and yes steam has passed through


Aiming for 0900 start on Wednesday. Jobs to do include pointing the contraction gaps so compo mixing, further top ballasting, levelling L&Y tunnel approach, fitting new point to L&Y tunnel access line. General tidying up and movement of old stuff to the covered station. Plus loads of other bits.