Tunnel walls Finished


Main tunnel walls were finished today. Tunnel floor has been cleaned ready for concrete on Monday. Please DO NOT walk through the new tunnel. 

Sunday's work revolves around finishing the timber at the portal end ready for concrete on Monday.  Water pipe needs routing through the drain pipe near toilets.  All traffic must use an alternative route to get to far end of tunnel. 

MONDAY is concreting day we will need help please. 